    IGCC电站与燃气轮机组电站的优势比较

    Comparison between IGCC power plant and gas turbine power plant

    • 摘要: 为了对比IGCC电站与燃气轮机组电站,对中电投廊坊2×400 MW级IGCC项目和中电投廊坊2×400 MW级燃气热电工程中的数据进行分析,并参考中美2×400 MW级IGCC发电系统及华能天津临港经济区2×400 MW级燃气热电联产工程等项目,分别从大气污染物排放执行标准,实际可能达到的排放指标,电站的投资、固定成本、可变成本、单位成本等技术经济的角度对IGCC电站和燃气轮机组电站进行了比较。结果表明,两者环境排放指标相当,但IGCC电站主要单位成本约为燃气轮机组电站的62.2%,采用IGCC电站替代燃煤电站要优于燃气轮机组电站替代燃煤电站。

       

      Abstract: In order to make an objective comparison between IGCC power plant and gas turbine power plant,the data from two finished projects of China Power Investment Corporation Langfang,which were 2 × 400 MW IGCC power plant project and 2 × 400 MW gas thermal power engineering were analyzed. The operating experience of China and United States 2 × 400 MW IGCC power system and China Huaneng Group Tianjin Lingang economic zone 2 × 400 MW gas cogeneration engineering projects had good reference value. From the technical economic angle on IGCC power plant and gas turbine power plant,the emissions of air pollutants standard,actual attainable emissions targets,investment,fixed cost,variable cost,per unit cost and so on were compared. The results showed that the two plants had roughly similar emissions,while the cost of IGCC power plant was 37. 8% less than the cost of gas turbine power plant,so IGCC power plant was a more advantage alternative.

       

    /

    返回文章
    返回